Teams X and Y work separately on two different projects.
On sunny days, team X can complete the work in 12 days
while team Y needs 15 days.
On rainy days, team X’s efficiency decreases by 50%
while team Y’s efficiency decreases by 25%.
Given that the two teams started and ended the projects at the same time,
how many rainy days are there?.

阿弥陀佛 2009-4-19 11:12

12.

哈哈爸 2009-4-19 15:38

回复 2#阿弥陀佛 的帖子

谢谢,能给出过程吗?.

阿弥陀佛 2009-4-20 22:51

回复 3#哈哈爸 的帖子

设:晴天x天,雨天y天,两人总工程量分别为A,B。

1/12Ax+1/12A*(1-50%)y=A

1/15Bx+1/15B*(1-25%)y=B

x=6,y=12.